View Subprojects | Migration Debian | Gantt Chart | Import/Export CSV

Tasks That Depend on This Task

Submitted by:
Laurent DELAGE(ladelage)
Permalink:
https://adullact.net/pm/t_follow.php/309
 
Category:
None
Task Detail Information (JSON):
application/json or text/plain
 
Percent Complete:
100%
Priority:
3
Subscribe to task
Start Date:
2004-12-07
End Date:
2004-12-14
 
Task Summary:
Envoyer le couillu au CRI74
Original Comment:
Transférer physiquement le couillu au CRI avec une debian SARGE de base ...
Assigned to
felie
ladelage
Dependent on task
Poser le serveur noir en Backup
Hours
8
Status
Closed
 
Task Id Task Summary
310 Basculer la production

No Related Tracker Items Have Been Added

No Comments Have Been Posted

Task Change History

Field Old Value Date By
status_id 1 2005-02-09 09:02 ladelage
percent_complete 0 2005-02-01 15:28 ladelage
FEDER Powered By FusionForge Collaborative Development Environment Charte d'utilisation / Nous contacter / Mentions légales Haut de page