View Subprojects | Migration Debian | Gantt Chart | Import/Export CSV

No Tasks are Dependent on This Task

No Related Tracker Items Have Been Added

Comments: Sort comments antichronologically

Submitted by:
Laurent DELAGE(ladelage)
Permalink:
https://adullact.net/pm/t_follow.php/310
 
Category:
None
Task Detail Information (JSON):
application/json or text/plain
 
Percent Complete:
100%
Priority:
3
Subscribe to task
Start Date:
2004-12-14
End Date:
2004-12-21
 
Task Summary:
Basculer la production
Original Comment:
Upct.org redevient le couillu au CRI74
Assigned to
bondaz_mi
felie
ladelage
malvypierre
Dependent on task
Envoyer le couillu au CRI74
Hours
25
Status
Closed
 
Comment Date By
Le serveur Upct.org redevient le couillu au CRI74 2004-11-15 14:03 ladelage

Task Change History

Field Old Value Date By
status_id 1 2005-02-09 09:02 ladelage
percent_complete 0 2005-02-01 15:28 ladelage