View Subprojects | Outils de gestion | Gantt Chart | Import/Export CSV
|
Submitted by: Philippe Allart (pallart) |
Permalink: https://adullact.net/pm/t_follow.php/104 |
|||||
|
Category: None |
Task Detail Information (JSON): application/json or text/plain |
|||||
|
Percent Complete: 0% |
Priority: 3 |
|
||||
|
Start Date: 2003-05-19 |
End Date: 2003-06-02 |
|||||
|
Task Summary: Règles de gestion |
||||||
|
Original Comment: Définir les règles à appliquer au momemnt de la création et de la modification d'un concept. |
||||||
|
|
|||||
|
Hours 16 |
Status Open |
|||||
| Task Id | Task Summary |
|---|---|
| 105 | Développement d'une maquette |
No Related Tracker Items Have Been Added
No Comments Have Been Posted
Task Change History
| Field | Old Value | Date | By |
|---|---|---|---|
| end_date | 2003-05-09 | 2003-05-03 20:24 | pallart |
| summary | Règles de ggestion | 2003-04-26 20:24 | pallart |